If you are planning to buy a new crane, the most important number may not be the price. It is the delivery date.

Right now, new crane deliveries are running from about six months for a few models to eleven months or a year for others. Used cranes are not an easy way around it either: good units are hard to find, and the ones that come up move quickly.

Here is how we help customers plan around that, and where time can realistically be saved.

The best fix is planning early

The most common problem we see is not the lead time itself. It is ordering when the lift is due instead of when the project is planned.

If a project is going to need a crane in a year, the time to order is now. By the time the job is mobilizing, the options have narrowed to whatever happens to be available, and that rarely matches the machine the job actually needs.

A simple rule: as soon as a project with a crane requirement is confirmed, start the crane conversation in parallel with the rest of the planning.

Choosing the right model can save weeks or months

Lead times are not the same across a manufacturer's range. Some models and configurations ship sooner than others.

In many cases, more than one model can do the job. A crane with slightly different capacity, boom length or configuration may cover the same lifts and arrive weeks or months earlier. Knowing which options are realistic for the job, and which are closer to available, is where an experienced dealer earns its place.

We help customers compare options against the actual lift plan, not just the spec sheet, so the choice is about the work, not only the model name.

When a used unit makes sense

In rare cases, a used or low-hour crane can close the gap. It takes flexibility:

  • The right unit may be in another country.
  • It may not match your ideal configuration exactly.
  • It has to be inspected properly before anyone commits to it.

When a used unit is the right answer, we can send a technician to inspect the crane where it is, handle the paperwork and produce a written report so you can decide with full information. If you go ahead, we can hand the crane to your logistics team or move it all the way to your site. The choice is yours.

Technician inspecting crane components before purchase
Technician inspecting crane components before purchase

Waiting versus compromising

Every lead time decision comes down to a comparison: the cost of waiting for the ideal crane versus the cost of a compromise that arrives sooner. That includes rental costs in the meantime, schedule penalties, and the long-term fit of the machine for your fleet.

There is no single right answer, but there is a wrong way to make the decision: too late, with no options left.

You can see the cranes we offer on our Link-Belt cranes page, and our inspection and support services on our service page.

Tell us the job and the date

Send us the type of work, the lifts you need to make, where the crane will operate and when you need it on site. We will tell you honestly what is realistic and which options can get you there soonest.